|
|
Capture and Control Data in the Global Marketplace - "Best CM Practices" |
Return books within 30 days for a full refund if not entirely satisfied
|
|
1. In the first state, Designer
Control, the design is initiated and controlled by the designer. Control of the
design data is in the hands of the designer. He or she can use any means at their disposal
or within their range of preferences to manage these design data. Your designers
only constraints are those imposed upon them by the system level specification, which
defines the product requirements. This specification is the output of Design Review #1,
and is immediately placed under Configuration Control, i.e., via a Configuration Control
Board (CCB). Appendix A provides a detailed description of how Design Reviews should
function in your Engineering Development process and how they should be utilized for CM
planning and execution. Your Functional Baseline (system level) and Allocated Baselines
(subsystem level) are established at this point. 2. In the second state, Design Internal, the level of control (still informal) is increased because at that point, an event has occurred which establishes the expectation of a certain amount of goodness in the design, and the design efforts of other people may be impacted by changes to your design as you move into your prototype build phase. In the example presented herein, that event is Design Review #2. The designer has enough confidence in his design to sign the drawing and turn it over to your engineering development laboratory to start construction of your prototype hardware. Proposed changes to the design must be approved by the design lead. It is your lead design engineers responsibility to communicate with other functional areas and personnel proposed changes, which may impact their design activities. These two states are generally referred to as Work-In-Progress (WIP). 3. At the conclusion of Design Review #3, there is sufficient
confidence in the design to justify the procurement of production hardware. This event
triggers the transition to the Formal
Internal state. At this point, the design database is updated, the design data
are fed into your businesss manufacturing inventory and ordering system, and initial
(or all) orders are placed for production hardware. Future proposed changes to the design (including changes to the system level specifications) are documented on your internal change notices and are approved or disapproved by your internal Configuration Control Board (CCB). Unless otherwise negotiated, your customer should not participate in the change approval process until the Product Baseline has been established, as defined below. Your Functional Configuration Audit (FCA) is conducted on the engineering prototype during the Formal Internal state. The purpose of the FCA is to assure that tests have been conducted to verify that each requirement specified in the system level specification has been met by the design. If tests cannot be performed to verify a particular requirement, then a theoretical error analysis must be performed to verify satisfactory compliance to the requirement. These tests are generally referred to as Design Evaluation and Qualification tests. They are used primarily on military product programs. The purpose of these activities is universal, though and should be an integral part of every development program. 4. The transition to the External state occurs at the successful
completion of the FCA. This event initiates the conduct of the Physical Configuration
Audit (PCA). During the PCA, the engineering drawings are proofed by comparison to the
first production unit. This unit should be built to manufacturing planning that was
created from the engineering drawing package. Measurements are verified and all
instructions, processes and technical data specified on the engineering drawings are
verified against the hardware. Historically, many businesses referred to this activity as
the First Article Inspection (FAI). The second major activity of the PCA is
the capture of drawing revision and serial number data and comparison to
as-defined revision levels plus verification that serial numbers have not been
previously used. The final activity of the PCA is the performance of an Acceptance Test
(AT) to assure that the unit examined is physically and functionally the same as the unit
that passed the FCA. Your Product Baseline is established at this point. By conducting your CM activities, tasks and duties per the instructions provided in Appendix B and structured in accordance with the methodology represented by the four state level of control system model, you will be assuring the establishment of best CM practices within your organization. |